B-421018.2, .3

  • The protester alleged that GSA failed to conduct meaningful discussions by not raising, in pre-corrective action discussions, significant weaknesses that resulted in the proposal being rated unacceptable in a post-corrective action evaluation.
  • GAO has held that, when an agency seeks revised proposals and performs a new evaluation, that reevaluation may identify flaws in a materially unchanged proposal that the agency would have been required to discuss with the offeror, had the flaws been identified when the proposal was initially evaluated.
  • In that situation, the agency must reopen discussions in order to disclose its concerns.