Tips to Maximize Contractor Recoveries for Public Health-Related Claims: Lessons from Pernix Serka and the Ebola Crisis

Government Contracts Navigator

Does the mere existence of a deadly epidemic entitle a contractor to monetary relief when it experiences cost increases stemming from that epidemic? Not without Government direction, ruled the Federal Circuit in affirming a decision of the Civilian Board of Contract Appeals (“CBCA”) in Pernix Serka JV.

The facts of Pernix Serka are striking: a contractor repeatedly requests guidance for dealing with a major health crisis, the Government refuses to provide guidance, and the contractor is unable to recoup the additional costs it incurs in order to proceed with performance because the Government provided no guidance.

This timely ruling sheds light on strategies contractors should consider for recouping costs stemming from the COVID-19 pandemic. We provide a roadmap below for navigating these issues in light of Pernix Serka JV.

The 2014 Ebola Crisis

Pernix Serka was in the midst of performing a contract in Sierra Leone when a deadly Ebola outbreak struck the country in 2014. Pernix Serka diligently sought guidance from the Contracting Officer on its State Department (“DOS”) contract, but the Government refused to weigh in on whether it should temporarily shut down its work on the contract. Ultimately, Pernix Serka decided to temporarily withdraw its personnel, which the Government then characterized as Pernix Serka’s “unilateral” decision. When Pernix Serka sought advice on whether and when to resume work, the Government went so far as to say that “DOS will not provide any instructions or directions” regarding whether and when to return to the work site. The contractor ultimately decided to resume performance, but incurred additional costs when it decided to contract for medical facilities and services on the project site.